Work is now underway on a £1.6 million project to replace bearings under the bridge deck of the Clyde viaduct.
The 140-year-old viaduct supports a great deal of weight and volume of trains on a daily basis, meaning the existing bearings have begun to show signs of deterioration.
The three span, 90 metre, steel structure stands on three sandstone piers above the River Clyde near Uddingston and carries traffic on the strategically important West Coast Mainline, as well as local services.
The bearings sit between the bridge deck and the piers and serve to control movement in the structure and absorb stresses generated by trains travelling above.
Work is now underway on a £1.6 million project to replace bearings under the bridge deck of the Clyde viaduct - which carries strategically important West Coast mainline over #RiverClyde near #Uddingston.
— NetworkRail Scotland (@NetworkRailSCOT) August 29, 2018
More details here https://t.co/nagBxwqagS pic.twitter.com/m2WtJm7Bod
Twelve sliding bearings in total, four on the east abutment and eight on the west pier need to be replaced.
The new steel bearings are one metre long and half a metre wide and because of their modern design, they are less bulky than those they are replacing and will be set on pre-cast slabs which will have a combined weight of around 1.5 tonnes each
Every bridge we work on has its own set of challenges but replacing bearings on this type of structure within constraints of railway environment is unique; logistics, engineering, physical size of space to work in & sheer weight of bearings going in & coming out. #Uddingston pic.twitter.com/a9oQmG6NxF
— NetworkRail Scotland (@NetworkRailSCOT) August 29, 2018
The team have been on site for 3 months now undertaking preparatory work on the bridge before even touching the bearings themselves. As well as creating the scaffolding and hoist system, the team have strengthened and braced the bridge and prepared sections of the structure around the bearings in readiness for jacking-up for the work – with the first bearing set to be removed on Saturday 1 September.
Work will be on going until December and delivered with no disruption to train service.
As well as the logistical challenges of working at height above a river, the Network Rail team and specialist contractor Taziker also have to work within the restricted space under the bridge deck to firstly insert hydraulic jacks to take the weight of the bridge and raising it a maximum of 5mm. The bolts will then be drilled out and the old bearings removed and replaced.
One bearing will be removed and replaced at a time over the next 12 weeks with three of the 12 being replaced when the line is closed overnight Saturday into Sunday.
The other nine will be removed and replaced while trains continue to run above.
Jeremy Spence, Network Rail’s programme manager, said: “Our structures are subject to a regular programme of inspection and routine minor maintenance which allows us to monitor their condition and react if any faults develop or the condition deteriorates to a point where we need to intervene.
“Having reached that point on the Clyde viaduct, the challenge from an engineering perspective was to come up with a way to replace the bearings while keeping the railway open.
“Every bridge we work on has its own set of challenges but replacing bearings on this type of structure within the constraints of the railway environment is unique; logistics, engineering, the physical size of the space we have to work in and the sheer weight of the bearings going in and coming out.
"Add to that the element of the unknown in how a century old bridge deck will react to being jacked and how easily, or not, the bearings will be removed, has certainly focused minds on this task”.
The scaffolding will be removed and the site compound cleared by December 2018.
Comments & Moderation
Readers’ comments: You are personally liable for the content of any comments you upload to this website, so please act responsibly. We do not pre-moderate or monitor readers’ comments appearing on our websites, but we do post-moderate in response to complaints we receive or otherwise when a potential problem comes to our attention. You can make a complaint by using the ‘report this post’ link . We may then apply our discretion under the user terms to amend or delete comments.
Post moderation is undertaken full-time 9am-6pm on weekdays, and on a part-time basis outwith those hours.
Read the rules here