A £3.5 MILLION programme to improve weather resilience on the main Glasgow-Edinburgh railway line is set to begin.
The nine-month project will see Network Rail and contractor QTS carry out crucial work between Croy and Dullatur to help prevent speed restrictions from having to be imposed during periods of heavy rain, meaning there will be less disruption for passengers.
Services into Glasgow Queen Street will be affected on Sunday, April 16 and passengers are urged to check their journey at scotrail.co.uk
Engineers are starting to clear vegetation and will be upgrading drainage systems as well as installing high-strength mesh, soil nails and rock bolts on embankments to help prevent wash-outs and rock falls.
READ MORE: 'Locked up and forgotten': Local group takes over historic graveyard
Jeremy Spence, Network Rail senior programme manager, says they will do all they can to limit disruption.
He said: "This work will help us manage the increasing periods of severe weather and the challenges they present for the railway.
"We will be keeping the community updated as our plans progress and will do all we can to limit disruption.
"We thank those living near the railway, and station users, for their patience while we deliver this critical improvement to Scotland’s Railway."
To carry out the work safely and to minimise disruption to services, engineers will complete some of the work at night.
A section of Croy station car park will also be used as a compound for the project and access to the nearby footpath will be required during points of the programme to carry out crucial work.
Andy Steel, operations director for QTS, said: "QTS is pleased to be working alongside Network Rail to deliver this critical project which will ultimately improve the rail service on the Edinburgh-Glasgow line.
"As part of the works, we will be utilising QTS specialist rope access operatives, alongside our plant and machinery, to ensure that this project is carried out safely and efficiently.
"Our team will work hard to minimise the impact that these works may have on the neighbouring communities and the passengers and commuters who use this line."
Comments & Moderation
Readers’ comments: You are personally liable for the content of any comments you upload to this website, so please act responsibly. We do not pre-moderate or monitor readers’ comments appearing on our websites, but we do post-moderate in response to complaints we receive or otherwise when a potential problem comes to our attention. You can make a complaint by using the ‘report this post’ link . We may then apply our discretion under the user terms to amend or delete comments.
Post moderation is undertaken full-time 9am-6pm on weekdays, and on a part-time basis outwith those hours.
Read the rules hereLast Updated:
Report this comment Cancel