An urgent update has been revealed on the closure of the M8 over the Easter weekend.
We reported that essential overnight maintenance was being carried out on the eastbound M8 between Junctions 19 and 15 and westbound M8 between Junctions 16 and 18.
This would be done in several phases throughout 2024.
However, Amey on behalf of Transport Scotland has said the works will be paused during the Easter weekend.
Eastbound works will stop on Thursday, March 28 at 6am and recommence on Sunday, April 7 at 10pm.
Westbound works will now begin on Tuesday, April 2 at 10pm.
Works will then continue to follow the timeline outlined below.
Eastbound
Closures will start with Phase Two of the eastbound works which will take place between Sunday, March 17 and Friday, May 10 from 10pm until 6am, each night, excluding weekend nights.
Eastbound work will be carried out using overnight closures only, Sunday to Friday, on the following dates: March 17 to March 22, March 24 to March 29, April 7 to April 12, April 28 to May 3, May 5 to May 10.
Signs for the following diversions will be in operation:
Eastbound M8 traffic will come off the M8 at junction 18 (St George's Road) onto St George's Road, then onto Garscube Road, Dobbie's Loan, then back onto the M8 at junction 16 (Craighall).
There will be eastbound slip road closures at junctions 19 and 18 (Charing X) with traffic being directed to North Street and St George's Road to join the main diversion.
Westbound
Phase One of westbound works will take place between Sunday, March 31 and Friday, May 24 from 10pm until 6am, each night, excluding weekend nights.
Westbound work will be carried out using overnight closures only, Sunday to Friday, on the following dates: March 31 to April 5, April 14 to April 19, April 21 to April 26, May 12 to May 17, May 19 to May 24.
Signs for the following diversions will be in operation:
Traffic will exit the M8 at junction 16 (Craighall), following the diversion westbound to Dobbie's Loan. Traffic will then drive southbound on Garscube Road, approaching westbound West Graham Street before joining back onto the M8 westbound via junction 17 westbound on-slip.
This diversion will be as follows between April 4 and 6 and will return to the above diversion on April 7:
Traffic will exit the M8 at junction 16 (Craighall), following the diversion westbound to Dobbie's Loan. Traffic will then be directed to Cowcaddens Road, approaching westbound West Graham Street before joining back onto the M8 westbound via junction 17 westbound on-slip.
Access for emergency service vehicles will not be maintained throughout these works.
Comments & Moderation
Readers’ comments: You are personally liable for the content of any comments you upload to this website, so please act responsibly. We do not pre-moderate or monitor readers’ comments appearing on our websites, but we do post-moderate in response to complaints we receive or otherwise when a potential problem comes to our attention. You can make a complaint by using the ‘report this post’ link . We may then apply our discretion under the user terms to amend or delete comments.
Post moderation is undertaken full-time 9am-6pm on weekdays, and on a part-time basis outwith those hours.
Read the rules here